METODE PELAKSANAAN DAN ANALISA BIAYA BEKISTING PADA PEKERJAAN STRUKTUR (STUDI KASUS: PEMBANGUNAN GEDUNG ASTRA HONDA MOTOR SEMARANG)
ABSTRACT: The analysis of
management constructionin the implementation of development projectsneeds to be
done in order to obtain an effective construction methods and cost
efficient.The purpose of this study is to compare two methods of formwork on
each floor plate to get a more feasible method applied is based on the time and
cost of the project. Stages in conducting the study are:Calculation of the
volume of work on projects that include foundation work, tie beams, columns,
beams, plates, ladder, shearwall, GWT (Ground Water Tank). Cost calculation on
project work, in order to get the cost for all elements of the building
structure. Calculation of the power plate and beams in project work, for the
purposes of dismantling formwork manually, with estimate the time of the plate
and beam formwork to release. Comparison of two implementation methods of
calculation of the work on the first fabrication of formwork plate method done
at the beginning of the three floors, while the second method of fabrication of
formwork is onlydone at the beginning of the two floors. Comparison of plate
work and the work done by the time and the project costs (direct and indirect
costs). Implementation of management analysis performed in order to obtain an
effectiveconstruction methods and cost efficient, so the comparison of the
results of both methods can be concluded that the second method is more
efficient and can be applied to the implementation of the project, with the
difference in cost Rp.277 288 777, - and the difference in duration of work is
5 days longer.
Penulis: Budi Rohmad
Wijayanto, M. Yudi Purnawan, Sukamta, Arif Hidayat
Kode Jurnal: jptsipildd140504