Analisis Faktor-Faktor Penyebab Perbedaan Estimasi Biaya Awal Dengan Biaya Pelaksanaan Proyek Konstruksi di Lingkungan Kampus Politeknik Negeri Padang
Abstract: The difference
preliminary cost estimate often do so at the cost of implementation of
construction projects. Likewise with construction projects in the country
Polytechnic Padang. The research that has been conducted found that the factors
that cause differences in the cost of government policies change often with a
contribution of 2.221%, 1.487% of the project schedule, a change of plans for
the implementation of the project amounted to 1.098%, 1.036 criteria for
project drawings %, review the design of 0.955%, the first disbursement of
funds are not clear 0.850%, the processes of implementation on the ground of
0.720%, rising material prices rising by 0.614% and 0.550% of wages.