Analisis Faktor-Faktor Penyebab Perbedaan Estimasi Biaya Awal Dengan Biaya Pelaksanaan Proyek Konstruksi di Lingkungan Kampus Politeknik Negeri Padang

Abstract: The difference preliminary cost estimate often do so at the cost of implementation of construction projects. Likewise with construction projects in the country Polytechnic Padang. The research that has been conducted found that the factors that cause differences in the cost of government policies change often with a contribution of 2.221%, 1.487% of the project schedule, a change of plans for the implementation of the project amounted to 1.098%, 1.036 criteria for project drawings %, review the design of 0.955%, the first disbursement of funds are not clear 0.850%, the processes of implementation on the ground of 0.720%, rising material prices rising by 0.614% and 0.550% of wages.
Key Word: cost estimate, construction projects, project schedule, project amounted
Penulis: Monika Natalia, Yan Partawijaya,  Satwarnirat, Rahmi Hidayati, Hartati