PENJADWALAN MESIN DENGAN MENGGUNAKAN ALGORITMA PEMBANGKITAN JADWAL AKTIF DAN ALGORITMA PENJADWALAN NON-DELAY UNTUK PRODUK HYDROTILLER DAN HAMMERMIL PADA CV. CHERRY SARANA AGRO
Abstract: Fulfillment of all
demands of consumers
who come to the product is one thing
that always wanted to be achieved
by a company. These requests are not independent of the company's ability to
manufacture certain products. CV Cherry Sarana Agro manufactures a wide range of
agricultural equipment, one of
which is the product
hydrotiller and hammermil.
Demand for both products are always in large numbers for each period,
however, the company could not meet the
entire demand. One
of the main
factors that led
this small company's production capacity
for these two
products is not
optimal scheduling of
machines made by companies,
causing many to
be a queue
on a particular
machine so that
the total process operating time becomes very large.
Scheduling method is used to optimize the scheduling of machines working
on the report of this practice is actively scheduling method and the method of
non-delay scheduling. The data needed to perform scheduling with both of these
methods is the data used machines, data processing operations and data
processing time of operation. With these three data, can be compared to the
actual scheduling done by the company with the scheduling is done using active
scheduling method and the method of non-delay scheduling.
The most optimal
scheduling is obtained
after comparing the
three methods used
are scheduling using the
non-delay scheduling. This
method was chosen
because the resulting make span is much smaller than the
two other methods. This method is well applied in the company because
in addition to
reducing the total
processing time, can
also increase production
capacity, so that all requests can be met.
Penulis: Prima Fithri, Fitri
Ramawinta
Kode Jurnal: jptindustridd130345