PERENCANAAN PENGGANTIAN JEMBATAN JUWET KABUPATEN PEMALANG
ABSTRACT: Juwet Bridge is located
approximately one kilometer to the south of Comal Bridge Pemalang District is
one of the alternative bridges used when the Comal Bridge collapsed. In this
final Juwet Bridge which has a width of only 3 meters is designed with a larger
capacity and functioned as an alternative pathway Comal Bridge. Planning on
aspects of traffic using a design life of 20 years with the growth of the
vehicle based on a linear regression of 642 veh / year and using two scenarios,
there are normal conditions (2 Comal Bridge function) and incidental conditions
(only 1 Comal Bridge functioning). Initial planning, the alternative pathway
using a type 2/2 UD. In normal conditions, the distribution of traffic flow 70%
for Comal Bridge and 30% for Juwet Bridge produce a degree of saturation (DS)
under 0.75 over the life of the plan. In the incidental conditions, the
distribution of traffic flow 60% for Comal Bridge and 40% for Juwet Bridge, DS
value is 0.81. Assuming then use 2/2 type UD with 8 meters wide still used. New
Juwet Bridge continue to use steel as the structure and the upper structure of
reinforced concrete for the structure underneath. Planned implementation within
8 months at a cost of Rp. 36.4 billion. In this final project scope of the
planned bridge elements include work for the overall structure of the bridge
and approach bridge. Given this new Juwet Bridge when congestion occurs on the
Pantura line around Comal Bridge, the bridge is able to be an alternative
pathway in servicing and reducing the burden of most of the traffic flow on the
Pantura line.
Penulis: Andhy Satriya
Wardhana, Mohamad Irzam Hasani, Moga Narayudha, Siti Hardiyati
Kode Jurnal: jptsipildd150165