ANALISA PERCEPATAN PROYEK METODE CRASH PROGRAM STUDI KASUS: PROYEK PEMBANGUNAN GEDUNG MIXED USE SENTRALAND
ABSTRACT: When the
implementation of construction projects, there are several barriers that are
often experienced and can cause delays. According to Presidential Decree No. 54
of 2010 delays can incur a penalty of 1/1000 of the contract price. Delays can
be taken to help accelerate the work. Scheduling a project conceived for the
target specified time can be achieved. Scheduling has a series of activities
related and have a total duration of the longest (critical path). Crash program
is a way to accelerate the estimated costs required to reduce the time work on
the critical path. Calculation begins with finding the critical path then
perform crashing to obtain cost slope. Mixed Use Building Project Sentraland
delayed, the author wants to analyze the time and cost of accelerating the work
with method of program crashes. The normal duration for the structure 7 to
Floor Roof Floor Level (Floor RL) is 203 days, at a cost of Rp 36,718,664,136.
The acceleration process is divided into three (3) scenarios. Scenario 1 Job
Fields with crashing duration of 191 days and costs Rp 36,907,386,256, Scenario
2 Plates Works Floor and Beam with a duration of 188 days and costs Rp
37,759,094,653, Scenario 3 Employment Column, Plates Floor and Beam with a duration
of 176 days and cost Rp 37,930,808,077. Of the value of cost slope and a graph
of cost and time, acceleration is obtained optimum point Scenario 1
Penulis: Restu Rama Bayu Adi,
Devinta Elga Traulia, M. Agung Wibowo, Frida Kistiani
Kode Jurnal: jptsipildd160253