REDESIGN LAYOUT WORKSTATION PROSES INJECTION MOLDING BERDASARKAN WORKLOAD ANALYSIS DAN PROSES SIMULASI PADA PEMBUATAN KOMPONEN LCDTV
ABSTRACT: Productivity
improvement of the company can be reach with many effort, which are minimizing
waste, improving the utility of operator, and also redesigning layout
facilities. Based on the observation, idle time of operator for the injection
process is 30 minutes. If the delay will be compare with the company losses, it
is equal to IDR. 1.001.700/operator/month. Based on this problem, redesign of
the facilities layout is a solution to improve utilities and workload of
operator. The result of this research, alternative layout has design based on
simulation and the analysis of Activity Relationship Chart (ARC). It could be
minimized the material handling 49.4 meters and 42.9 seconds. For the financial
analysis, it can be minimized the labour cost IDR 14.684.670/month and also the
material handling cost at least IDR 54.262/month.
Penulis: Fajar Mulyana, Sugiono,
Ishardita Pambudi Tama
Kode Jurnal: jptindustridd150107