ANALISIS SISTEM PENGENDALIAN BIAYA (COST CONTROL FRAMEWORK) PADA PROYEK PELEBARAN JALAN SP.3 LEMPAKE SAMARINDA - SP.3 SAMBERA KALIMANTAN TIMUR
ABSTRACT: In this study, will
be analyzed Cost control framework on one road construction project in East
Kalimantan using Earned Value Concept and Work Break Down Structure. As the
object ofstudy is Sp.3 Road Widening Project Lempake (Dublin) - Sp.3 Sambera
located in the city ofSamarinda, East Kalimantan. way of acquiring primary data
through observation and interviews directly to the project, while secondary
data from project documents.
Performance costs and time by using Earned Value Concept in terms of the
reporting week 25 CV and SV value value Positive Negative, indicating that the
work has been delayed from the timethe work plan, but the cost is still below
the budgeted costs. Resource use efficiency using Earned Value Fund at week-25
values of 1.11 and SPI CPI of 0.93. Cost performance, while showing good
performance for performance efficiency by less well because of a delay of the
planned time. Predicted cost and project completion time estimated the cost for
the remaining work on theassumption that the trend of the performance of the
project will remain until the end of the project(ETC) amounted to Rp 3, 138,305,144.17
while the estimated cost of up project completion (EAC)is equal to = Rp.
9,871,988,500.07, which means there is no advantage or still under the budget
plan (PV) in the amount of Rp. 10,968,876,111.19. While the estimated schedule
for the completion of the aspects of the job completion time estimates obtained
(TE) assuming the performance trend ofthe project remains is 212 days. This
means that the project will be delayed approximately 14 daysof 198 days plan.
Penulis: Edward Prana,
M.Ruslin Anwar, Yulvi Zaika
Kode Jurnal: jptsipildd120297